MindMap Gallery The process from project establishment to construction start
This is a mind map about project establishment. The main contents include: project establishment, start of construction, construction project construction permit, construction project planning permit, real estate certificate, construction land planning permit, feasibility study report, environmental impact assessment approval, selection Site opinion letter, land use preliminary review.
Edited at 2024-04-22 09:36:30Mappa mentale per l’analisi del controllo della gestione del portata di progetto. Tre sezioni principali: 1. WBS Scope Breakdown – scomposizione gerarchica del lavoro con dettaglio dello Scopo del progetto. 2. Scope Boundary / Exclusions – definizione chiara dei confini del progetto e di ciò che è escluso per evitare scope creep. Strumento ideale per project manager e team di controllo per mantenere allineamento e ridurre rischi.
Questo template, ideato con EdrawMind, è un modello completo per il miglioramento continuo del sistema di gestione della qualità, con una descrizione di circa 500 parole. È strutturato come un diagramma a lisca di pesce, strumento efficace per analizzare le cause principali dei problemi di qualità e definire le leve di controllo necessarie per risolverli. Il processo è organizzato in quattro fasi chiave: la prima è lo standard e la pianificazione, dove si definiscono gli obiettivi di qualità, i criteri di accettazione, i requisiti di prova e le porte di qualità (Quality Gate). La seconda fase analizza i processi e le porte di controllo, per garantire che ogni passaggio del lavoro segua i standard stabiliti. La terza fase riguarda l’esecuzione QA/QC, con la definizione di metodi di prova e ispezione, nonché regole per la gestione dei difetti e delle non conformità. L’ultima fase è il miglioramento e le azioni correttive e preventive (CAPA), insieme a una catena di audit per monitorare l’efficacia delle misure adottate. In basso, una tabella "Quality Gate" permette di tracciare ogni punto di controllo, con criteri specifici, metodi di prova, proprietario e stato di avanzamento. Grazie alla visualizzazione chiara e intuitiva di EdrawMind, questo strumento aiuta il team a identificare le cause root dei problemi di qualità, implementare azioni efficaci e mantenere un ciclo di miglioramento continuo, garantendo la qualità finale del prodotto o servizio.
Questo template, creato con EdrawMind, è un modello di piano di comunicazione ottimizzato, con una descrizione di circa 500 parole. È uno strumento chiave per evitare incomprensioni tra stakeholder, garantire la trasparenza e mantenere il team allineato agli obiettivi del progetto. Il modello è composto da tre elementi fondamentali e interconnessi: la matrice di comunicazione, la cadenza timeline e le regole di comunicazione/SLA. La matrice di comunicazione è una tabella dettagliata dove per ogni pubblico o stakeholder, si definisce il tipo di informazioni da condividere, lo scopo della comunicazione, il canale da utilizzare (email, riunioni, piattaforme di progetto), la frequenza, il proprietario responsabile, il formato e il percorso di escalazione in caso di problemi. La cadenza timeline è una linea temporale che definisce le scadenze delle comunicazioni chiave, garantendo che le informazioni siano condivise in momento opportuno e non si verifichino ritardi o omissioni. Le regole di comunicazione e gli accordi sul livello di servizio (SLA) definiscono le norme formali della comunicazione, come i tempi di risposta, il tono da adottare e le responsabilità di ciascun membro del team. Grazie alla struttura visuale di EdrawMind, questo template permette di pianificare la comunicazione in modo strategico, trasparente e efficiente, riducendo i rischi di cattiva informazione, migliorando la collaborazione e garantendo che tutti gli stakeholder siano informati e coinvolti nel progetto.
Mappa mentale per l’analisi del controllo della gestione del portata di progetto. Tre sezioni principali: 1. WBS Scope Breakdown – scomposizione gerarchica del lavoro con dettaglio dello Scopo del progetto. 2. Scope Boundary / Exclusions – definizione chiara dei confini del progetto e di ciò che è escluso per evitare scope creep. Strumento ideale per project manager e team di controllo per mantenere allineamento e ridurre rischi.
Questo template, ideato con EdrawMind, è un modello completo per il miglioramento continuo del sistema di gestione della qualità, con una descrizione di circa 500 parole. È strutturato come un diagramma a lisca di pesce, strumento efficace per analizzare le cause principali dei problemi di qualità e definire le leve di controllo necessarie per risolverli. Il processo è organizzato in quattro fasi chiave: la prima è lo standard e la pianificazione, dove si definiscono gli obiettivi di qualità, i criteri di accettazione, i requisiti di prova e le porte di qualità (Quality Gate). La seconda fase analizza i processi e le porte di controllo, per garantire che ogni passaggio del lavoro segua i standard stabiliti. La terza fase riguarda l’esecuzione QA/QC, con la definizione di metodi di prova e ispezione, nonché regole per la gestione dei difetti e delle non conformità. L’ultima fase è il miglioramento e le azioni correttive e preventive (CAPA), insieme a una catena di audit per monitorare l’efficacia delle misure adottate. In basso, una tabella "Quality Gate" permette di tracciare ogni punto di controllo, con criteri specifici, metodi di prova, proprietario e stato di avanzamento. Grazie alla visualizzazione chiara e intuitiva di EdrawMind, questo strumento aiuta il team a identificare le cause root dei problemi di qualità, implementare azioni efficaci e mantenere un ciclo di miglioramento continuo, garantendo la qualità finale del prodotto o servizio.
Questo template, creato con EdrawMind, è un modello di piano di comunicazione ottimizzato, con una descrizione di circa 500 parole. È uno strumento chiave per evitare incomprensioni tra stakeholder, garantire la trasparenza e mantenere il team allineato agli obiettivi del progetto. Il modello è composto da tre elementi fondamentali e interconnessi: la matrice di comunicazione, la cadenza timeline e le regole di comunicazione/SLA. La matrice di comunicazione è una tabella dettagliata dove per ogni pubblico o stakeholder, si definisce il tipo di informazioni da condividere, lo scopo della comunicazione, il canale da utilizzare (email, riunioni, piattaforme di progetto), la frequenza, il proprietario responsabile, il formato e il percorso di escalazione in caso di problemi. La cadenza timeline è una linea temporale che definisce le scadenze delle comunicazioni chiave, garantendo che le informazioni siano condivise in momento opportuno e non si verifichino ritardi o omissioni. Le regole di comunicazione e gli accordi sul livello di servizio (SLA) definiscono le norme formali della comunicazione, come i tempi di risposta, il tono da adottare e le responsabilità di ciascun membro del team. Grazie alla struttura visuale di EdrawMind, questo template permette di pianificare la comunicazione in modo strategico, trasparente e efficiente, riducendo i rischi di cattiva informazione, migliorando la collaborazione e garantendo che tutti gli stakeholder siano informati e coinvolti nel progetto.
Project establishment
Project establishment
The development and reform department will approve the construction in the form of a document on the "Project Proposal" or "Pre-Feasibility Study Report".
The approval of the project establishment report is one of the basis for the feasibility study topic.
When many projects are applied for project approval, the conditions are relatively mature, and land, planning, environmental impact assessment, professional consulting opinions, etc. are basically in place. In particular, the source of project funds is entirely self-raised by the project legal person, with no financial funds and no special policies. This type of project It is often a project establishment report (substituting for a feasibility study report), and the two stages are combined into one stage.
The review and approval of the project proposal basically takes 7 working days to complete, and the validity period of the project proposal approval is usually two years.
Preliminary review of land use
The natural resources department shall review the land use matters involved in the construction project in accordance with the law during the approval, verification and filing stages of the construction project.
When the project construction unit applies for approval or approval of a construction project to the development and reform departments, it must attach the pre-examination opinions of the land and resources department.
The processing time for project land pre-examination and site selection opinion letter issuance is approximately 20 working days, and the promised processing time is 10 working days.
Site Selection Opinion Letter
Opinions on site selection for construction projects and pre-examination opinions on land use for construction projects are merged. The natural resources authorities will uniformly issue pre-examination opinions on land use for construction projects and opinions on site selection. They will no longer issue separate opinions on site selection for construction projects and pre-examination opinions on land use for construction projects separately.
The pre-examination of project land and the preparation of site selection opinions are prerequisites for the approval of the feasibility study.
The processing time for project land pre-examination and site selection opinion letter issuance is approximately 20 working days, and the promised processing time is 10 working days.
Environmental impact assessment approval
After the project obtains the approval of the project proposal, it can proceed with the land use pre-examination, site selection submission and environmental impact assessment procedures simultaneously.
The construction unit shall, in accordance with the provisions of the "Classified Management Directory of Environmental Impact Assessment of Construction Projects", organize the preparation of construction project environmental impact reports, environmental impact report forms or fill in the environmental impact registration forms respectively.
The environmental protection administrative department shall make respective approval decisions within 60 days from the date of receipt of the environmental impact report of the construction project, within 30 days from the date of receipt of the environmental impact report form, and within 15 days from the date of receipt of the environmental impact registration form. Notify the construction unit in writing.
Projects that prepare environmental impact assessment reports (forms) should obtain approval at the latest before starting construction; those who fill in an environmental impact assessment registration form should complete the filing before putting into operation.
feasibility study report
A feasibility study report means that before engaging in an economic activity (investment), both parties must conduct specific investigations, research, and analysis on various factors such as economy, technology, production, supply and marketing, as well as various social environments, laws, etc., to determine the favorable and unfavorable factors. , whether the project is feasible, and estimates the success rate, economic benefits and social effects.
A prerequisite for the approval of the feasibility study report is the completion of the land pre-examination and site selection opinion letter.
We promise to make a decision on the feasibility study report within 3 working days (the legal time limit is 20 days) from the date of acceptance of the application.
Construction land planning permit
The construction land planning permit is a legal certificate that the construction land meets the requirements of urban and rural planning after being reviewed by the urban and rural planning authorities in accordance with the law.
Construction land planning licenses are issued by the municipal and county natural resources authorities to the construction unit.
For administrative licensing, if the construction land planning license and the construction project planning license are handled uniformly or jointly or centrally, the processing time shall not exceed 45 days.
Real estate title certificate
The real estate certificate is proof that the obligee enjoys the property rights of the real estate.
The ownership certificate can also be used as evidence of the existence of rights, but it is not the main basis for confirming rights. Even if the ownership certificate is transferred to another person, if there is no change in property rights recorded in the registered content, the property rights themselves will not change.
After obtaining the construction land planning permit, the construction unit can apply for land from the local Natural Resources Management and Planning Bureau.
The real estate registration agency shall complete the real estate registration procedures within 30 working days from the date of accepting the registration application, unless otherwise provided by law.
Construction project planning license
The construction project planning permit is a legal certificate that the construction project meets the requirements of urban and rural planning after being reviewed by the urban and rural planning authorities in accordance with the law.
If a construction project planning license is not obtained or construction is not carried out in accordance with the provisions of the construction project planning license, the urban and rural planning department of the local people's government at or above the county level shall order the construction to stop; if corrective measures can still be taken to eliminate the impact on the implementation of the plan, the construction project shall be ordered to stop within a time limit. If corrections are made, a fine of not less than 5% but not more than 10% of the construction project cost will be imposed; if corrective measures cannot be taken to eliminate the impact, the project will be demolished within a time limit. If it cannot be demolished, the physical property or illegal income will be confiscated, and a fine of not more than 10% of the construction project cost may be imposed.
According to the Urban and Rural Planning Law of the People's Republic of China, the legal processing time limit is 20 working days.
Construction project construction license
A construction project construction license is an approval document that the construction unit meets various construction conditions and is allowed to start construction. It is a legal certificate for the construction unit to carry out project construction, and is also one of the main basis for the registration of house ownership.
The two most basic prerequisites for applying for a construction project construction license are to obtain a construction project planning license and a real estate certificate.
After applying for a construction license and meeting the conditions, the construction administrative department shall issue a construction license to the qualified application within seven days from the date of receipt of the application.
The construction unit shall start construction within three months from the date of obtaining the construction permit. If the construction cannot be started on time for any reason, an extension shall be applied to the license-issuing authority; the extension shall be limited to two times, each time not exceeding three months. If construction neither starts nor applies for an extension or exceeds the extension time limit, the construction permit will be automatically revoked.
Construction