MindMap Gallery Engineering management mind map
This is a mind map about project management. The main contents include: completed data status and status of projects in progress. Welcome to like and collect~
Edited at 2024-03-05 08:22:50Avatar 3 centers on the Sully family, showcasing the internal rift caused by the sacrifice of their eldest son, and their alliance with other tribes on Pandora against the external conflict of the Ashbringers, who adhere to the philosophy of fire and are allied with humans. It explores the grand themes of family, faith, and survival.
This article discusses the Easter eggs and homages in Zootopia 2 that you may have discovered. The main content includes: character and archetype Easter eggs, cinematic universe crossover Easter eggs, animal ecology and behavior references, symbol and metaphor Easter eggs, social satire and brand allusions, and emotional storylines and sequel foreshadowing.
[Zootopia Character Relationship Chart] The idealistic rabbit police officer Judy and the cynical fox conman Nick form a charmingly contrasting duo, rising from street hustlers to become Zootopia police officers!
Avatar 3 centers on the Sully family, showcasing the internal rift caused by the sacrifice of their eldest son, and their alliance with other tribes on Pandora against the external conflict of the Ashbringers, who adhere to the philosophy of fire and are allied with humans. It explores the grand themes of family, faith, and survival.
This article discusses the Easter eggs and homages in Zootopia 2 that you may have discovered. The main content includes: character and archetype Easter eggs, cinematic universe crossover Easter eggs, animal ecology and behavior references, symbol and metaphor Easter eggs, social satire and brand allusions, and emotional storylines and sequel foreshadowing.
[Zootopia Character Relationship Chart] The idealistic rabbit police officer Judy and the cynical fox conman Nick form a charmingly contrasting duo, rising from street hustlers to become Zootopia police officers!
Wu Weixin
Project status in progress
Quanzhou Affiliated Middle School of Fujian Normal University-Quanzhou No.15 Middle School Dual Power Supply Renovation
G:
High-voltage cable: 755 meters laid
Low-voltage cables: 4 revamped, totaling 260 meters (after changes)
Fund situation: 897,577 yuan; 90% of the original contract stipulated before power delivery; not paid yet.
Planned power delivery time: None
Progress status: High-voltage cables have been laid, but low-voltage cables have not been laid (no new progress as of 0219)
There is a problem: the group called for suspension, the contract needs to be re-signed, and there is no new progress as of February 26
Kinmen Water Supply Water Source Guarantee Nangao Main Canal Water Supply Replacement Project Good G-01 Working Well
Project introduction: One 800kVA box transformer, 123 meters of high-voltage cables, 6 new wells and 100*2 meters of buried pipes
Funding situation:
Total contract cost: 8736387 (fixed unit price); payment method: 90% before power delivery
This project (G-01): 937,906 yuan
Planned power delivery time: None
Progress: Equipment has been ordered (no new progress as of 02.26)
Problems exist: The location of the 4-meter height difference between the box-type transformer foundation and the road surface (backfilled by the user) has not yet been confirmed. The soil quality was surveyed on-site on 02.21 and was not backfilled. It is expected that construction can begin in 20 days.
Jinli Avenue Infrastructure Electricity Project
Infrastructure changes in the eastern section of Jinli Avenue
Project introduction: 138 meters of high-voltage cable, one 630kVA box transformer (rental)
Power was delivered on February 1st
Infrastructure changes in the west section of Jinli Avenue
Project introduction: Assemble 5 cables, one 630kVA box transformer (rental), 35 meters of high-voltage cable
Planned power delivery time: early March
Progress: The foundation of the box-type transformer has been completed, and the line is expected to be put into operation at 02.27.
There is a problem: the wire crosses the ancestral home, and the user coordinates the line corridor on 02.26 afternoon
Fund situation: 284,287 yuan; 0206 pays all fees.
Quanzhou Liyuan Industrial Development Co., Ltd. - "Quanzhou Licheng District High-tech Zone Science and Technology Innovation Center" Standardized Industrial (Industrial) Park Power Supply and Distribution Project
Low voltage section
Assessment meters: 8
Number of user meters: 3
There are problems: not all meters are installed, and low-voltage cables are at risk of being stolen.
Completion information
The electrical part and bridge part have been sorted out
It can only be submitted after standardized statistics and integration.
Quanzhou Economic and Technological Development Zone Park Construction Co., Ltd.-Detai Road Night Market Project
Project introduction: 129 meters of high-voltage cable, one 500kVA box transformer, 3*2 meters of pipe trench, and one foundation
Fund situation: 268,361 yuan
Contract signing time: 02.06, it is agreed that all payments will be made 7 days after the contract is signed.
Not paid as of 02.26
Planned power delivery time: None (35 working days after the contract is signed); the user requires power delivery on March 1
Progress: The transformer has been ordered by 0220, and the foundation is planned to be excavated on February 27.
Problems: lack of electrician certificate; 02.21 The group coordinated the change of transformer model s20 to s13. The basic drawing of the transformer has been issued, but the change drawing has not been released.
Completion information
The official power supply project of the Quanzhou Affiliated Middle School of Fujian Normal University-Quanzhou No.15 Middle School Expansion Project
Users require settlement first and then signature
Sent for settlement, lack of material list
Quanzhou Licheng District Jiangnan High-tech Zone Urban Development Co., Ltd.-Changtai Central Primary School New Power Distribution Project
Users require settlement first and then signature
The settlement has been sent, and the civil engineering part is being modified.
Fujian Quanzhou City Comprehensive Development Co., Ltd.-Mantangli Life Infrastructure Electricity Project
Completion documents have been signed
It was delivered to the user before the holiday. The user indicated that the moving company would deliver it after the holiday.
Fujian Torch Electronic Technology Co., Ltd. (Torch Electronic Supercapacitor Project) Project
Standardization has been completed, there are air holes in the ground, and rectification is required (already rectified)
Completion data: The data will be consolidated after statistics on the standardized work surface
The remaining 7% of the project payment is about 470,000, which has not been paid
Project outside the red line of Science and Technology Innovation and Hi-tech Park
There is a problem
The manhole cover is undergoing rectification
Emergency repair of Zhenfu Lane switch office
Completion data is being compiled
20240226 Summary
Wu Weixin
Project status in progress
Quanzhou Affiliated Middle School of Fujian Normal University-Quanzhou No.15 Middle School Dual Power Supply Renovation
G:
High-voltage cable: 755 meters laid
Low-voltage cables: 4 revamped, totaling 260 meters (after changes)
Funding situation:
Account arrival status:
contract
Contract amount: 897,577 yuan; 90% of the original contract stipulated before power delivery; has not been paid.
Planned power delivery time:
none
Progress:
High-voltage cables have been laid, but low-voltage cables have not been laid (no new progress as of 0219)
There is a problem:
The group called for suspension and the contract needs to be re-signed. No new progress has been made as of February 26.
Kinmen Water Supply Water Source Guarantee Nangao Main Canal Water Supply Replacement Project Good G-01 Working Well
G:
One 800kVA box transformer, 123 meters of high-voltage cables, 6 new wells and 100*2 meters of buried pipes
Funding situation:
Account arrival status
contract
This project (G-01): 937,906 yuan; payment method: 90% before power delivery
Planned power delivery time:
none
Progress:
The equipment has been ordered (no new progress as of 02.26)
There is a problem:
The location of the 4-meter height difference between the box-type transformer foundation and the road surface (backfilled by the user) has not yet been confirmed. The soil quality was surveyed on-site on 02.21 and no backfill was found. It is expected that construction can begin in 20 days.
Jinli Avenue Infrastructure Electricity Project
G
Infrastructure substation in the west section of Jinli Avenue: assemble 5 cables, one 630kVA box substation (rental), 35 meters of high-voltage cable
Funding situation:
Account arrival status
100%
contract
284,287 yuan; 0206 pays all fees.
Planned power delivery time
early March
Progress:
The eastern section is completed
The foundation of the box-type transformer in the western section has been completed, and the line is expected to be put into operation at 02.27.
There is a problem:
The wire crosses the ancestral home, and the user coordinates the line corridor on 02.26pm
Quanzhou Liyuan Industrial Development Co., Ltd. - "Quanzhou Licheng District High-tech Zone Science and Technology Innovation Center" Standardized Industrial (Industrial) Park Power Supply and Distribution Project
Low voltage section
Assessment meters: 8
Number of user meters: 3
There are problems: not all meters are installed, and low-voltage cables are at risk of being stolen.
Completion information
The electrical part and bridge part have been sorted out
It can only be submitted after standardized statistics and integration.
Quanzhou Economic and Technological Development Zone Park Construction Co., Ltd.-Detai Road Night Market Project
G:
129 meters of high-voltage cable, one 500kVA box transformer, 3*2 meters of pipe trench, and one foundation
Funding situation:
Account arrival status
0
contract:
Contract amount: 268,361 yuan; 100% after contract
Planned power delivery time:
(35 working days after the contract is signed); the user requires power delivery on March 1
Progress:
: 0220 The transformer has been ordered, and it is planned to enter the site to excavate the foundation on 02.27.
There is a problem:
Lack of electrician certificate; 02.21 The group coordinated the change of transformer model s20 to s13. The basic drawing of the transformer has been issued, but the change drawing has not been released.
Completion information
The official power supply project of the Quanzhou Affiliated Middle School of Fujian Normal University-Quanzhou No.15 Middle School Expansion Project
Users require settlement first and then signature
Sent for settlement, lack of material list
Quanzhou Licheng District Jiangnan High-tech Zone Urban Development Co., Ltd.-Changtai Central Primary School New Power Distribution Project
Users require settlement first and then signature
The settlement has been sent, and the civil engineering part is being modified.
Fujian Quanzhou City Comprehensive Development Co., Ltd.-Mantangli Life Infrastructure Electricity Project
Completion documents have been signed
It was delivered to the user before the holiday. The user indicated that the moving company would deliver it after the holiday.
Fujian Torch Electronic Technology Co., Ltd. (Torch Electronic Supercapacitor Project) Project
Standardization has been completed, there are air holes in the ground, and rectification is required (already rectified)
Completion data: The data will be consolidated after statistics on the standardized work surface
The remaining 7% of the project payment is about 470,000, which has not been paid
Project outside the red line of Science and Technology Innovation and Hi-tech Park
There is a problem
The manhole cover is undergoing rectification
Emergency repair of Zhenfu Lane switch office
Completion data is being compiled
Chen Hengda
Project status in progress
Quanzhou Municipal Engineering Center - 1# underground relocation project at the intersection of Weiwu Road and Jingshi Road (Donghai Investment Building General Contracting Project Telephone Pole Relocation Engineering Contract)
Project overview
100kVA underground transformer migration
Fund situation
Account arrival status
0%
contract
The contract price is 374,575 yuan, 100% after the contract
Planned power delivery time
2024.04.01
progress status
The change part has been completed.
There is a problem
The power point of the power supply scheme is wrong. The power supply scheme has been changed again.
Quanzhou Public Transport Group Co., Ltd.---Wenling Bus First and Last Station Power Distribution Project
Project overview
2*800kVA box transformer and civil pipe trench construction
Fund situation
Account arrival status
90%
contract
The contract price is 1.172561 million yuan, 30% of the contract price; 90% before power delivery
Planned power delivery time
Complete power transmission
progress status
Some pipe ditches on Wenling Road need to be combined with municipal construction
There is a problem
Quanzhou Fengze Fenggu Storage and Transportation Co., Ltd. Power Distribution Project
Project overview
1*630kVA box transformer and civil engineering
Fund situation
Account arrival status
50%
contract
The contract price is 327,507 yuan, 50% of the contract price; 95% before power delivery
Planned power delivery time
After the construction of the user pipeline is completed, it will be combined with the supporting construction of urban industry expansion.
progress status
User pipeline under construction
There is a problem
Quanzhou Administrative Center Phase I (main building and turnover room) emergency interface
Project overview
Generator power supply modification
Fund situation
Account arrival status
50%
contract
The contract price is 489,988 yuan, 50% of the contract; 50% before power delivery, 100% after power delivery
Planned power delivery time
Transformation completed
progress status
completed
There is a problem
Construction has been completed according to the drawings, power has been delivered, and the location of the meter box has been changed as required by the user.
Completion information
Liming Vocational University power line and new switching station project
Completion time
2023.11.06
Waiting for user third-party audit review
Quanzhou Advanced Technical School Power Capacity Expansion and Supporting Facilities Renovation Project (Phase I)
Completion time
2022.09.26
User third-party audit under review
The third phase of construction of Donghai Campus-Building G dormitory building, teaching building and lecture theater project
Completion time
2023.10.16
The completion data is already at the user's site, waiting for third-party review by the user.
Abandoned mine ecological restoration phase one demonstration section three-phase meter project
Completion time
2024.02.24
The completion data is being compiled and is waiting to be sent to the user for stamping.
Zhang Xiaoliang
Project status in progress
Quanzhou Construction Engineering Group Co., Ltd.--Newly built "Shui Mo Fanghua" residential community power supply and distribution project
G
2 new switching stations and power distribution rooms (8*630KVA) and 1 commercial power distribution room (1*1000KVA) were built.
Fund situation
Account arrival status
40% received
contract
The contract price is 11.365646 million yuan, 40% for equipment entry; 30% for completion acceptance before power delivery; 27% for equipment transfer to the property
Planned power delivery time
Preview March 2024
progress status
The on-site cable laying has been completed, and the terminals and intermediate joints of the incoming cables will be made on the day of the power outage. The debugging of electrical equipment has been completed, and the equipment manufacturer has been notified to rectify any problems with the equipment on site. The engineering changes were rolled back due to scheduling upgrades. On February 26, 2024, the change modeling was notified to be resubmitted. The power distribution room is under standardized construction and the sealing has been completed. The floor paint construction will begin on the 26th; preliminary inspection is scheduled for completion next week.
There is a problem
Standardized construction is relatively lagging behind, and the communication incoming optical cable has not yet been laid and spliced.
Quangang District Science and Technology Museum Transformer Capacity Increase Project
G
1 box transformer
Fund situation
Account arrival status
0
contract
Contract price 364,218 yuan
Planned power delivery time
Preview March 2024
progress status
Installation completed, suspended until payment is received
There is a problem
funding problem
Shishi City Emergency Water Source Jinshan Pumping Station Technical Renovation (Transformer Replacement) Power Distribution Project
G
Replace transformer
Fund situation
Account arrival status
100% credit received
contract
The contract price is 63,667 yuan, 100% after the contract
Planned power delivery time
Preview March 2024
progress status
The remaining instrument transformers in the metering cabinet are inconsistent with the ones on site and have not been replaced. The rest have been completed.
There is a problem
The purchased transformer does not match the site
Quanzhou Peiyuan Middle School Low Voltage Line Reconstruction Project
G
Low voltage cabinet renovation and low voltage cable laying
Fund situation
Account arrival status
298,750 yuan
contract
The contract price is 555,599 yuan, 30% after contract, 90% after completion
Planned power delivery time
2024.03.03
progress status
The remaining two low-voltage cables have not been laid, and as of February 26, 2024, all the cables have been laid. The power outage originally scheduled for the 25th was postponed to March 3 due to the school's coming-of-age ceremony;
There is a problem
Insufficient construction strength of the collaborative team
Huafu Building power distribution room capacity expansion project
G
Fund situation
Account arrival status
50%, the group marketing department has communicated with the user that the amount will be credited to 97% on the 27th (deducting 3% warranty deposit)
contract
The contract price is 628,982 yuan, 50% after the contract, 100% before power delivery
Planned power delivery time
2024.02.28
progress status
Complete acceptance
There is a problem
Insufficient construction strength of the collaborative team
Tianzhong Anshangfang Power Supply and Distribution Project EPC General Contracting (Plot 2)
G
1 switching room and 3 power distribution rooms, capacity 12*800kVA
Fund situation
Account arrival status
0
contract
0
Planned power delivery time
2024.06
progress status
On-site disclosure was made on February 23, 2024, and the bridge material has been ordered and scheduled for construction next week;
There is a problem
Quanzhou Highway Development Center’s newly installed 250kVA power distribution project
G
1 power distribution room, capacity 1*250kVA
Fund situation
Account arrival status
0
contract
The contract price is 199,500.00 yuan, and 100% will be paid within 10 working days after the contract is signed.
Planned power delivery time
2024.06
progress status
On-site disclosure was made on 2024.02.23, and orders for civil construction materials and electrical equipment were completed on the 26th.
There is a problem
none
Completion information
Completion information
Quanxiu Garden West District One House, One Table Renovation Project
Completion time
2023.12
The revised completion data has been completed and will be submitted for the supervisor’s signature on February 27. After completion, the user’s confirmation signature will be submitted.
Yang Xiaowei
Project status in progress
Quangang No. 2 Middle School Box Transformer Low Voltage Renovation Project (High School)
Project overview
New box-type transformer capacity: 800kVA one set, dual power supply transformation and partial low-voltage transformation.
Fund situation
Account arrival status
0
contract
subtopic
Planned power delivery time
none
progress status
The high-voltage dual power supply transformation and power transmission were completed, and the low-voltage transformation cables were ordered. However, due to unpaid user payments, the project was suspended.
There is a problem
The user's project payment has not been paid, and the project is suspended.
Nanpu Central Primary School-Nanpu Second Central Kindergarten, Quangang District, Quanzhou City 400KVA power distribution project
G
Build a new 400KVA box transformer
Fund situation
Account arrival status
30% received
contract
Total contract price: 634,567 yuan, 85% of the total project price is payable 10 working days before completion and power delivery.
Planned power delivery time
none
progress status
Completion acceptance on September 8, 2023. The project payment was not paid and the project was suspended.
There is a problem
No project fees were paid as stipulated in the contract.
Quanzhou Quangang New City Investment Co., Ltd. applied for 800KVA infrastructure transformation project (fishing port section)
Project overview
Quanzhou Quangang New City Investment Co., Ltd. applied for 800kVA infrastructure transformation project (fishing port section)
Fund situation
Account arrival status
0
contract
Total contract price: 216,873. The contract stipulates 85% after passing the inspection.
Planned power delivery time
none
progress status
First completion acceptance on May 28, 2021. The second completion acceptance will be on October 16, 2023.
There is a problem
The user's project payment has not been paid.
Completion information
Lin You
Project status in progress
1. Quanzhou Sports Center Power Supply Switching Station Elimination of Safety Hazards Remediation Project 2023.03.14
Project overview:
Capacity expansion of 1000kVA and replacement of high-voltage cabinets in switching stations
Funding situation:
Arrival status: 0
The contract stipulates: the amount is 1.074067 million yuan, 90% before power delivery
Planned power delivery time
2024.01.15
Progress:
Construction will be completed and the last power outage will be restored after the funds are in place.
There is a problem:
2. Quanzhou Entry-Exit Border Inspection Station of the People's Republic of China - Fujian Border Guard Corps Quanzhou (Southern Fujian) Border Inspection Troop Barracks Power Distribution Project
Project overview
:4*800KVA
Fund situation
Arrival status: 30%
The contract stipulates that the amount is 7,525,537 yuan, and the contractor shall pay an advance payment of 30% of the total contract price within 7 working days after signing. 90% before power transmission
Planned power delivery time
2024.02.25
Progress:
The remaining one well for backup power supply is under construction, the backup cable has not been laid, and the others have been inspected and accepted.
There is a problem:
Funds are not in place before power delivery
3. EPC general contracting of power supply and distribution project in Jinmei Resettlement Area (Comprehensive Development Company)
Project overview:
1 switching room and power distribution room 2*630kVA, 2*800kVA
Funding situation:
Arrival status: 30%
The contract stipulates that the amount is 8.254388 million yuan.
Planned power delivery time:
2024.02.28
Progress:
Change order 20240102 submission data group
There is a problem:
Common room cables have not arrived
4. Power distribution project of the inpatient building of the Donghai Branch of the Second Affiliated Hospital of Fujian Medical University
Project overview:
2*1250kVA 2*1600kVA
Funding situation:
Account arrival status
contract:
Planned power delivery time:
2024.02.29
Progress:
Completion acceptance on February 2nd
There is a problem:
Civil construction is lagging behind, high-voltage cables have not arrived, and funds have not been allocated.
5. Quanzhou Huida Garment Weaving Co., Ltd. added two 800kVA transformers.
Project overview
2*800kVA
Funding situation:
Arrival status: 20%
The contract stipulates: The amount is 790,016 yuan, 20% after the contract; 50% after the equipment and 30% before power delivery.
Planned power delivery time:
None yet
Progress:
Civil engineering users are constructing by themselves
There is a problem:
6. Quanzhou Yiyuanchang Real Estate Development Co., Ltd.—New decoration project of Yuanchang Jiangnancheng Community
Project overview:
40*800kVA
Funding situation:
Account arrival status:
contract:
Planned power delivery time:
: None yet
Progress:
The two backup power supplies are not powered, and the rest are completed.
There is a problem:
High-voltage cable supply has not arrived yet
7. Donghai Tahoe
Project overview:
Two dedicated lines for access
Funding situation:
Payment status: 100%
contract
Planned power delivery time:
2024.03
Progress:
The special line of Zhongyunzhou Transformation has not been completed, and the rest have been completed.
There is a problem:
8. EPC general contracting of Tianzhong Anshang House power supply and distribution project (Plot 2)
G
2 switching stations and 5 power distribution rooms with a capacity of 20*800kVA
Fund situation
Account arrival status
0
contract
0
Planned power delivery time
2024.06
progress status
On-site disclosure was made on February 23, 2024, and the bridge material has been ordered and scheduled for construction next week;
There is a problem
9. Sub-project of Sanjin Cultural and Sports Industrial Park of the Second Affiliated Hospital of Fujian University
Project overview:
Distribution box and metering retrofit
Funding situation:
Arrival status: 30%
contract
Planned power delivery time:
60 days construction period
Progress:
Site survey
There is a problem:
Completion information
none
Chen Pingyang
Status of projects in progress
Nanshan District Qiaoxi Phase I Santai Street Light Transformation and Distribution Project
Project overview
Changes in Santai street lights
Fund situation
Account arrival status
0%
contract
The contract price is 346,606 yuan, 100% after the contract
Planned power delivery time
Arrival status: 0
progress status
pause
There is a problem
Payment unpaid
Jinsheng Travel Products Factory Community Power Distribution Project
Project overview
Backup power supply access, property rights transfer
Fund situation
Account arrival status
100%
contract
Original engineering company project
Planned power delivery time
None yet
progress status
Property rights, acceptance, submitted to major customers, current problems are being rectified
There is a problem
1. There is no secondary power supply in the power distribution room. DC screen should be configured. 2. There should be physical separation between the main business and the equipment to be transferred. 3. The power distribution room should be standardized. 4. Low-voltage lines should be pasted with nameplates as required. 5. The burial depth of high-voltage cables is insufficient. 6. Will there be any problem of adding charging piles in the future?
Quanzhou Wanan Commercial Central District Office Building Power Distribution Project
Project overview
One 1600, one 1000 dual power supply
Fund situation
Account arrival status
0%
contract
No contract
Planned power delivery time
May
progress status
February 4 civil engineering electrical appliances disclosure
Civil construction started on February 26
There is a problem
The incoming line path is occupied by sewage pipes
It has been coordinated to go above the sewage pipe
Quanzhou City Heshan Primary School Renovation and Expansion Project
Project overview
Two 250 box transformers
Fund situation
Account arrival status
0%
contract
The contract price is 268,321 yuan, 95% after contract
progress status
The civil foundation has been completed and the box transformer is in production
On February 5, the box-type transformer came into the site. On February 26, the cables were installed and debugged and accepted.
Information situation
Compilation of completion data has begun
There is a problem
none
Planned power delivery
March 1
Tonghai Community Ecological Parking Lot Project
Project status
A 315 box transformer
Fund situation
Account arrival status
0%
contract
The contract price is 661,328 yuan, 40% after the contract; 35% after entering the market, and the settlement is 100%
Planned power delivery time
Completion data has been compiled
progress status
Cable trench and box transformer foundation have been completed
There is a problem
Due to the long holiday, the owner negotiated for post-holiday remittance and box-type transformation.
Planned power delivery
March 15
Luobin North Road Street Light Renovation and Reconstruction Project
Project overview
A street lamp changes
Fund situation
Account arrival status
0%
contract
The contract price is 343,294 yuan, 90% of the price is 7 days before power delivery.
Planned power delivery time
April, completion data is being compiled
progress status
The foundation of the box transformer has been completed
There is a problem
There has been a change in the box-type transformer and pipe trench. The amount of work has increased. The operation department has been notified and the owner has signed a supplementary agreement to increase the cost of another change in the box-type transformer and pipe trench.
Not signed yet
Capacity expansion project of Fujian Hongguan Packaging Technology Co., Ltd.
Project status
Increase the capacity of a 1000 dry transformer
Fund situation
Progress payments have been made as agreed in the contract
Account arrival status
20%
contract
The contract price is 309,024 yuan, 20% after contract; 50% after entry into the market,
Planned power delivery time
2024.04 copies
progress status
The equipment has been brought to the site, and the cable entry pipe trench and panel foundation is under construction.
There is a problem
The incoming line path to the user's power point is blocked
Coordination has been completed and construction is ready
Completion information
Quangang Qingyuan Innovation Laboratory Power Distribution System Expansion Project
Completion time
2024.01.09
Completion data supervision is verifying and signing
Quangang No. 1 Middle School Dual Power Supply and Low Voltage Part Renovation Project
Completion time
2023.05.28
The business department’s Zhihui docking is temporarily unable to handle settlement. Quangang Finance has no allocation.
Quangang District UNESCO Industrial Development Co., Ltd. Quangang District Temporary Power Project
Completion time
2024.02.03
The bill of materials is being processed and the settlement will be sent this week.
Quanzhou City Luojiang District Heshi Health Center Power Distribution Renovation Project
Completion time
2024.02.02
Sent settlement
Yongjia Tiandi F Dikuai residential community power supply and distribution project 10 kV cable and wire project
Completion time
2024.02.06
The settlement information is being sorted.
Xu Yanjie
Projects in progress
Newly built power supply and distribution project for "Leju Chunhua" residential community
G
Two new switching stations, four power distribution rooms and one commercial power distribution room were built. Capacity: 8*800 8*630 2*1250
Fund situation
Contract stipulation: Not provided in the contract
Receipt status: None
Planned power delivery time
March 22
progress status
All the equipment has arrived, and the equipment for inspection is in place. The power distribution room is currently being installed once and twice. The low-voltage cable section cannot be installed due to the unavailability of elevators in some buildings, resulting in meter boxes, distribution boxes and cables. Changes repeatedly urged the team to submit. The person in charge, Lu Xianrui, has been notified and requested to submit it to maintenance no later than this week.
There is a problem
The elevators in some buildings on site were unavailable. We communicated with the owner on the 18th and the owner responded that he would arrange for the elevator manufacturer to cooperate as soon as possible.
Quanzhou Donghaiwan Experimental School Capacity Increase and Distribution Project
G
Add one 800-capacity transformer and low-voltage part
Fund situation
The contract stipulates that the total price is fixed at 381,403 yuan, 85% is paid before power delivery, and 97% is paid after settlement.
Receipt status: None
Planned power delivery time
April
progress status
Construction will begin after the team resumes work
There is a problem
none
Zhongjun Juxiang Business Center 2# switch station
G
A new opening and closing office was built
Fund situation
The contract stipulates: total price lump sum
Arrival status: Payment has been made as per the contract.
Planned power delivery time
The switch office has completed power transmission
progress status
The 2# switch station has completed power transmission. It is planned to arrange for the cable from the 1# switch station to the 3# distribution room to be reconnected to the 2# switch station after the holiday.
There is a problem
none
Quanzhou Municipal Archives Complex Building and Three-dimensional Parking Building Supporting Electrical Engineering
G
A new power distribution room, capacity: 1600*6 units
Fund situation
The contract stipulates: fixed unit price, contract amount 8,609,602 yuan. 30% after the contract is signed, 80% after the equipment is brought into the site, 90% before power delivery, and 97% after settlement.
Arrival status: Payment has been made as per the contract.
Planned power delivery time
Power delivery completed on January 25
progress status
The power transmission was completed on January 25. Due to the on-site owner's failure to lay low-voltage cables, the floor paint of the power distribution room could not be applied. It is planned to arrange standardized ground construction after the holiday.
There is a problem
none
Quanzhou Jinling Real Estate Development Co., Ltd. Jinwei Yiyuan Villa Area incoming power supply project
G
Construction of the second incoming line power supply
Fund situation
Payment has been made according to the contract
Payment has been made according to the contract
Planned power delivery time
none
progress status
The construction of high-voltage cables and overhead lines has been completed. Because Luojiang maintenance requires the owner to provide approval procedures for the line corridor, the owner cannot provide it, and the maintenance does not agree to the power transmission and handover.
There is a problem
The line corridor involves corridors along the railway line, and the owner cannot provide approval procedures. Maintenance does not agree to power transmission and handover
Completion information of projects in progress
none
Lin Guirong
1. Quanzhou Entry-Exit Border Inspection Station of the People's Republic of China - Fujian Border Guard Corps Quanzhou (Southern Fujian) Border Inspection Troop Barracks Power Distribution Project
progress status
98%
There is a problem
The remaining cable ducts connecting the sidewalks will need to be constructed until workers enter the site on February 27 (planned to be completed in four days)
2Power distribution project of the inpatient building of the Donghai Branch of the Second Affiliated Hospital of Fujian Medical University
Progress:
98%
There is a problem:
The remaining floor paint needs to be applied after the electrical installation is completed
Electric power connection project outside the Jiangnan New District project - Electric power drainage pipe construction outside the Jiangnan New District Science and Technology Innovation Center project
progress status
98%
There is a problem
The industrial manhole covers (ductile iron manhole covers) are being rectified and are promised to be completed on March 15
Fund situation: 6979192 yuan
Labor subcontracting 1,387,920 yuan
Progress payment of RMB 1,320,239 has been paid
Material subcontracting 3,330,884 yuan
Progress payment of RMB 3,221,669 has been paid
Professional subcontracting 2,260,388 yuan
Progress payment of RMB 1,307,206 has been paid
Wen Shaowei
Project status in progress
Mingji Xintiandi Phase II
Project overview: 1 new switch room and power distribution room (2*1250KVA) and 1 commercial power distribution room (2*1250KVA) will be built.
Funding situation:
Payment status: 50%
The contract stipulates: The amount is 5.827671 million yuan, 50% after the contract, 40% after the equipment comes into the site, and 10% before power delivery.
Planned power delivery time: 2023.09.21
Progress: One household per meter has been supplied with electricity and the property transfer procedures have been completed, but the commercial part has not been supplied with electricity.
Problem: Due to the bankruptcy of the real estate company, the court has ruled that our company has priority in repaying the remaining 50% of the project payment, and the operation department will follow up later.
Completion information
Fengquan Business - Nanpushan Shantytown Resettlement Housing Project Power Distribution Project
Our version of the completed data is not approved by the owner, and part of the cost of design changes has not been confirmed by the owner. After coordination with many parties, the completion data and change procedures are being reorganized according to their requirements. The as-built drawings have been reprinted and stamped with a completion stamp. The designer replied that he will be available to stamp the drawings and design stamp next week, and will go to Fuzhou to handle the stamping matter when the time is confirmed.
Xu Yanjie
Projects in progress
Newly built power supply and distribution project for "Leju Chunhua" residential community
G
Two new switching stations, four power distribution rooms and one commercial power distribution room were built. Capacity: 8*800 8*630 2*1250
Fund situation
Contract stipulation: Not provided in the contract
Receipt status: None
Planned power delivery time
March 22
progress status
All the equipment has arrived, and the equipment for inspection is in place. The power distribution room is currently being installed once and twice. The low-voltage cable section cannot be installed due to the unavailability of elevators in some buildings, resulting in meter boxes, distribution boxes and cables. Changes repeatedly urged the team to submit. The person in charge, Lu Xianrui, has been notified and requested to submit it to maintenance no later than this week.
There is a problem
The elevators in some buildings on site were unavailable. We communicated with the owner on the 18th and the owner responded that he would arrange for the elevator manufacturer to cooperate as soon as possible.
Quanzhou Donghaiwan Experimental School Capacity Increase and Distribution Project
G
Add one 800-capacity transformer and low-voltage part
Fund situation
The contract stipulates that the total price is fixed at 381,403 yuan, 85% is paid before power delivery, and 97% is paid after settlement.
Receipt status: None
Planned power delivery time
April
progress status
Construction will begin after the team resumes work
There is a problem
none
Zhongjun Juxiang Business Center 2# switch station
G
A new opening and closing office was built
Fund situation
The contract stipulates: total price lump sum
Arrival status: Payment has been made as per the contract.
Planned power delivery time
The switch office has completed power transmission
progress status
The 2# switch station has completed power transmission. It is planned to arrange for the cable from the 1# switch station to the 3# distribution room to be reconnected to the 2# switch station after the holiday.
There is a problem
none
Quanzhou Municipal Archives Complex Building and Three-dimensional Parking Building Supporting Electrical Engineering
G
A new power distribution room, capacity: 1600*6 units
Fund situation
The contract stipulates: fixed unit price, contract amount 8,609,602 yuan. 30% after the contract is signed, 80% after the equipment is brought into the site, 90% before power delivery, and 97% after settlement.
Arrival status: Payment has been made as per the contract.
Planned power delivery time
Power delivery completed on January 25
progress status
The power transmission was completed on January 25. Due to the on-site owner's failure to lay low-voltage cables, the floor paint of the power distribution room could not be applied. It is planned to arrange standardized ground construction after the holiday.
There is a problem
none
Quanzhou Jinling Real Estate Development Co., Ltd. Jinwei Yiyuan Villa Area incoming power supply project
G
Construction of the second incoming line power supply
Fund situation
Payment has been made according to the contract
Payment has been made according to the contract
Planned power delivery time
none
progress status
The construction of high-voltage cables and overhead lines has been completed. Because Luojiang maintenance requires the owner to provide approval procedures for the line corridor, the owner cannot provide it, and the maintenance does not agree to the power transmission and handover.
There is a problem
The line corridor involves corridors along the railway line, and the owner cannot provide approval procedures. Maintenance does not agree to power transmission and handover
Completion information of projects in progress
none
Chen Hengda
Project status in progress
Quanzhou Municipal Engineering Center - 1# underground relocation project at the intersection of Weiwu Road and Jingshi Road (Donghai Investment Building General Contracting Project Telephone Pole Relocation Engineering Contract)
Project overview
100kVA underground transformer migration
Fund situation
Account arrival status
0%
contract
The contract price is 374,575 yuan, 100% after the contract
Planned power delivery time
2024.04.01
progress status
The change part has been completed.
There is a problem
The power point of the power supply scheme is wrong. The power supply scheme has been changed again.
Quanzhou Public Transport Group Co., Ltd.---Wenling Bus First and Last Station Power Distribution Project
Project overview
2*800kVA box transformer and civil pipe trench construction
Fund situation
Account arrival status
90%
contract
The contract price is 1.172561 million yuan, 30% of the contract price; 90% before power delivery
Planned power delivery time
Complete power transmission
progress status
Some pipe ditches on Wenling Road need to be combined with municipal construction
There is a problem
Quanzhou Fengze Fenggu Storage and Transportation Co., Ltd. Power Distribution Project
Project overview
1*630kVA box transformer and civil engineering
Fund situation
Account arrival status
50%
contract
The contract price is 327,507 yuan, 50% of the contract price; 95% before power delivery
Planned power delivery time
After the construction of the user pipeline is completed, it will be combined with the supporting construction of urban industry expansion.
progress status
User pipeline under construction
There is a problem
Quanzhou Administrative Center Phase I (main building and turnover room) emergency interface
Project overview
Generator power supply modification
Fund situation
Account arrival status
50%
contract
The contract price is 489,988 yuan, 50% of the contract; 50% before power delivery, 100% after power delivery
Planned power delivery time
Transformation completed
progress status
completed
There is a problem
Construction has been completed according to the drawings, power has been delivered, and the location of the meter box has been changed as required by the user.
Completion information
Liming Vocational University power line and new switching station project
Completion time
2023.11.06
Waiting for user third-party audit review
Quanzhou Advanced Technical School Power Capacity Expansion and Supporting Facilities Renovation Project (Phase I)
Completion time
2022.09.26
User third-party audit under review
The third phase of construction of Donghai Campus-Building G dormitory building, teaching building and lecture theater project
Completion time
2023.10.16
The completion data is already at the user's site, waiting for third-party review by the user.
Abandoned mine ecological restoration phase one demonstration section three-phase meter project
Completion time
2024.02.24
The completion data is being compiled and is waiting to be sent to the user for stamping.
Zhang Xiaoliang
Project status in progress
Quanzhou Construction Engineering Group Co., Ltd.--Newly built "Shui Mo Fanghua" residential community power supply and distribution project
G
2 new switching stations and power distribution rooms (8*630KVA) and 1 commercial power distribution room (1*1000KVA) were built.
Fund situation
Account arrival status
40% received
contract
The contract price is 11.365646 million yuan, 40% for equipment entry; 30% for completion acceptance before power delivery; 27% for equipment transfer to the property
Planned power delivery time
Preview March 2024
progress status
The on-site cable laying has been completed, and the terminals and intermediate joints of the incoming cables will be made on the day of the power outage. The debugging of electrical equipment has been completed, and the equipment manufacturer has been notified to rectify any problems with the equipment on site. The engineering changes were rolled back due to scheduling upgrades. On February 26, 2024, the change modeling was notified to be resubmitted. The power distribution room is under standardized construction and the sealing has been completed. The floor paint construction will begin on the 26th; preliminary inspection is scheduled for completion next week. As of March 5: Except for the incoming communication optical fiber that has not been laid, the rest of the work on site has been basically completed, and the initial inspection will be completed on March 7.
There is a problem
The communication incoming optical cable has not yet been laid and spliced, and the process is lagging behind.
Quangang District Science and Technology Museum Transformer Capacity Increase Project
G
1 box transformer
Fund situation
Account arrival status
0
contract
Contract price 364,218 yuan
Planned power delivery time
Preview March 2024
progress status
Installation completed, suspended until payment is received
There is a problem
funding problem
Shishi City Emergency Water Source Jinshan Pumping Station Technical Renovation (Transformer Replacement) Power Distribution Project
G
Replace transformer
Fund situation
Account arrival status
100% credit received
contract
The contract price is 63,667 yuan, 100% after the contract
Planned power delivery time
Preview March 2024
progress status
The remaining instrument transformers in the metering cabinet are inconsistent with the ones on site and have not been replaced. The rest have been completed.
There is a problem
The purchased transformer does not match the site
Quanzhou Peiyuan Middle School Low Voltage Line Reconstruction Project
G
Low voltage cabinet renovation and low voltage cable laying
Fund situation
Account arrival status
298,750 yuan
contract
The contract price is 555,599 yuan, 30% after contract, 90% after completion
Planned power delivery time
2024.03.03
progress status
The remaining two low-voltage cables have not been laid. As of February 26, 2024, all the cables have been laid. The original power outage on the 25th was postponed to March 3 due to the school's coming-of-age ceremony; the power outage on the 3rd was reconnected to the new cabinet and restored. Power transmission, except for part of the civil construction ground that needs to be repaired, the rest of the work has been completed.
There is a problem
none
Huafu Building power distribution room capacity expansion project
G
Fund situation
Account arrival status
50%, the group marketing department has communicated with the user that the amount will be credited to 97% on the 27th (deducting 3% warranty deposit)
contract
The contract price is 628,982 yuan, 50% after the contract, 100% before power delivery
Planned power delivery time
2024.02.28
progress status
The acceptance inspection was completed. On the 27th, the pole-mounted switch was replaced with the industry expansion supporting equipment to complete the incoming cable connection and acceptance of power transmission. Except for some civil works on site, the overall project was completed.
There is a problem
none
Tianzhong Anshangfang Power Supply and Distribution Project EPC General Contracting (Plot 2)
G
1 switching room and 3 power distribution rooms, capacity 12*800kVA
Fund situation
Account arrival status
0
contract
0
Planned power delivery time
2024.06
progress status
On-site disclosure was made on February 23, 2024, and the bridge materials have been ordered and are scheduled to start construction next week; on March 6, the overall equipment and material order for the project was completed, and the civil construction has started.
There is a problem
Quanzhou Highway Development Center’s newly installed 250kVA power distribution project
G
1 power distribution room, capacity 1*250kVA
Fund situation
Account arrival status
0
contract
The contract price is 199,500.00 yuan, and 100% will be paid within 10 working days after the contract is signed.
Planned power delivery time
2024.06
progress status
On-site disclosure was made on February 23, 2024, and the ordering of civil construction materials and electrical equipment was completed on the 26th; on the 27th, the civil construction site was set out and excavated. The on-site civil construction foundation construction is in progress, and the equipment has been ordered.
There is a problem
none
Completion information
Completion information
Quanxiu Garden West District One House, One Table Renovation Project
Completion time
2023.12
The revised completion data has been completed and will be submitted for the supervisor’s signature on February 27. After completion, the user’s confirmation signature will be submitted.
Lin You
Project status in progress
1. Quanzhou Sports Center Power Supply Switching Station Elimination of Safety Hazards Remediation Project 2023.03.14
Project overview:
Capacity expansion of 1000kVA and replacement of high-voltage cabinets in switching stations
Funding situation:
Arrival status: 0
The contract stipulates: the amount is 1.074067 million yuan, 90% before power delivery
Planned power delivery time
2024.01.15
Progress:
Construction will be completed and the last power outage will be restored after the funds are in place.
There is a problem:
2. Quanzhou Entry-Exit Border Inspection Station of the People's Republic of China - Fujian Border Guard Corps Quanzhou (Southern Fujian) Border Inspection Troop Barracks Power Distribution Project
Project overview
:4*800KVA
Fund situation
Arrival status: 30%
The contract stipulates that the amount is 7,525,537 yuan, and the contractor shall pay an advance payment of 30% of the total contract price within 7 working days after signing. 90% before power transmission
Planned power delivery time
2024.02.25
Progress:
The remaining one well for backup power supply is under construction, the backup cable has not been laid, and the others have been inspected and accepted.
There is a problem:
Funds are not in place before power delivery
3. EPC general contracting of power supply and distribution project in Jinmei Resettlement Area (Comprehensive Development Company)
Project overview:
1 switching room and power distribution room 2*630kVA, 2*800kVA
Funding situation:
Arrival status: 30%
The contract stipulates that the amount is 8.254388 million yuan.
Planned power delivery time:
2024.02.28
Progress:
Change order 20240102 submission data group
There is a problem:
Common room cables have not arrived
4. Power distribution project of the inpatient building of the Donghai Branch of the Second Affiliated Hospital of Fujian Medical University
Project overview:
2*1250kVA 2*1600kVA
Funding situation:
Account arrival status
contract:
Planned power delivery time:
2024.02.29
Progress:
Completion acceptance on February 2nd
There is a problem:
Civil construction is lagging behind, high-voltage cables have not arrived, and funds have not been allocated.
5. Quanzhou Huida Garment Weaving Co., Ltd. added two 800kVA transformers.
Project overview
2*800kVA
Funding situation:
Arrival status: 20%
The contract stipulates: The amount is 790,016 yuan, 20% after the contract; 50% after the equipment and 30% before power delivery.
Planned power delivery time:
None yet
Progress:
Civil engineering users are constructing by themselves
There is a problem:
6. Quanzhou Yiyuanchang Real Estate Development Co., Ltd.—New decoration project of Yuanchang Jiangnancheng Community
Project overview:
40*800kVA
Funding situation:
Account arrival status:
contract:
Planned power delivery time:
: None yet
Progress:
The two backup power supplies are not powered, and the rest are completed.
There is a problem:
High-voltage cable supply has not arrived yet
7. Donghai Tahoe
Project overview:
Two dedicated lines for access
Funding situation:
Payment status: 100%
contract
Planned power delivery time:
2024.03
Progress:
The special line of Zhongyunzhou Transformation has not been completed, and the rest have been completed.
There is a problem:
8. EPC general contracting of Tianzhong Anshang House power supply and distribution project (Plot 2)
G
2 switching stations and 5 power distribution rooms with a capacity of 20*800kVA
Fund situation
Account arrival status
0
contract
0
Planned power delivery time
2024.06
progress status
On-site disclosure was made on February 23, 2024, and the bridge material has been ordered and scheduled for construction next week;
There is a problem
9. Sub-project of Sanjin Cultural and Sports Industrial Park of the Second Affiliated Hospital of Fujian University
Project overview:
Distribution box and metering retrofit
Funding situation:
Arrival status: 30%
contract
Planned power delivery time:
60 days construction period
Progress:
Site survey
There is a problem:
Completion information
none
Chen Pingyang
Status of projects in progress
Nanshan District Qiaoxi Phase I Santai Street Light Transformation and Distribution Project
Project overview
Changes in Santai street lights
Fund situation
Account arrival status
0%
contract
The contract price is 346,606 yuan, 100% after the contract
Planned power delivery time
Arrival status: 0
progress status
pause
There is a problem
Payment unpaid
Jinsheng Travel Products Factory Community Power Distribution Project
Project overview
Backup power supply access, property rights transfer
Fund situation
Account arrival status
100%
contract
Original engineering company project
Planned power delivery time
None yet
progress status
Property rights, acceptance, submitted to major customers, current problems are being rectified
There is a problem
1. There is no secondary power supply in the power distribution room. DC screen should be configured. 2. There should be physical separation between the main business and the equipment to be transferred. 3. The power distribution room should be standardized. 4. Low-voltage lines should be pasted with nameplates as required. 5. The burial depth of high-voltage cables is insufficient. 6. Will there be any problem of adding charging piles in the future?
Quanzhou Wanan Commercial Central District Office Building Power Distribution Project
Project overview
One 1600, one 1000 dual power supply
Fund situation
Account arrival status
0%
contract
No contract
Planned power delivery time
May
progress status
February 4 civil engineering electrical appliances disclosure
Civil construction started on February 26
There is a problem
The incoming line path is occupied by sewage pipes
It has been coordinated to go above the sewage pipe
Quanzhou City Heshan Primary School Renovation and Expansion Project
Project overview
Two 250 box transformers
Fund situation
Account arrival status
0%
contract
The contract price is 268,321 yuan, 95% after contract
progress status
The civil foundation has been completed and the box transformer is in production
On February 5, the box-type transformer came into the site. On February 26, the cables were installed and debugged and accepted.
Information situation
Compilation of completion data has begun
There is a problem
none
Planned power delivery
March 1
Tonghai Community Ecological Parking Lot Project
Project status
A 315 box transformer
Fund situation
Account arrival status
0%
contract
The contract price is 661,328 yuan, 40% after the contract; 35% after entering the market, and the settlement is 100%
Planned power delivery time
Completion data has been compiled
progress status
Cable trench and box transformer foundation have been completed
There is a problem
Due to the long holiday, the owner negotiated for post-holiday remittance and box-type transformation.
Planned power delivery
March 15
Luobin North Road Street Light Renovation and Reconstruction Project
Project overview
A street lamp changes
Fund situation
Account arrival status
0%
contract
The contract price is 343,294 yuan, 90% of the price is 7 days before power delivery.
Planned power delivery time
April, completion data is being compiled
progress status
The foundation of the box transformer has been completed
There is a problem
There has been a change in the box-type transformer and pipe trench. The amount of work has increased. The operation department has been notified and the owner has signed a supplementary agreement to increase the cost of another change in the box-type transformer and pipe trench.
Not signed yet
Capacity expansion project of Fujian Hongguan Packaging Technology Co., Ltd.
Project status
Increase the capacity of a 1000 dry transformer
Fund situation
Progress payments have been made as agreed in the contract
Account arrival status
20%
contract
The contract price is 309,024 yuan, 20% after contract; 50% after entry into the market,
Planned power delivery time
2024.04 copies
progress status
The equipment has been brought to the site, and the cable entry pipe trench and panel foundation is under construction.
There is a problem
The incoming line path to the user's power point is blocked
Coordination has been completed and construction is ready
Completion information
Quangang Qingyuan Innovation Laboratory Power Distribution System Expansion Project
Completion time
2024.01.09
Completion data supervision is verifying and signing
Quangang No. 1 Middle School Dual Power Supply and Low Voltage Part Renovation Project
Completion time
2023.05.28
The business department’s Zhihui docking is temporarily unable to handle settlement. Quangang Finance has no allocation.
Quangang District UNESCO Industrial Development Co., Ltd. Quangang District Temporary Power Project
Completion time
2024.02.03
The bill of materials is being processed and the settlement will be sent this week.
Quanzhou City Luojiang District Heshi Health Center Power Distribution Renovation Project
Completion time
2024.02.02
Sent settlement
Yongjia Tiandi F Dikuai residential community power supply and distribution project 10 kV cable and wire project
Completion time
2024.02.06
The settlement information is being sorted.
Yang Xiaowei
Project status in progress
Quangang No. 2 Middle School Box Transformer Low Voltage Renovation Project (High School)
Project overview
New box-type transformer capacity: 800kVA one set, dual power supply transformation and partial low-voltage transformation.
Fund situation
Account arrival status
0
contract
subtopic
Planned power delivery time
none
progress status
The high-voltage dual power supply transformation and power transmission were completed, and the low-voltage transformation cables were ordered. However, due to unpaid user payments, the project was suspended.
There is a problem
The user's project payment has not been paid, and the project is suspended.
Nanpu Central Primary School-Nanpu Second Central Kindergarten, Quangang District, Quanzhou City 400KVA power distribution project
G
Build a new 400KVA box transformer
Fund situation
Account arrival status
30% received
contract
Total contract price: 634,567 yuan, 85% of the total project price is payable 10 working days before completion and power delivery.
Planned power delivery time
none
progress status
Completion acceptance on September 8, 2023. The project payment was not paid and the project was suspended.
There is a problem
No project fees were paid as stipulated in the contract.
Quanzhou Quangang New City Investment Co., Ltd. applied for 800KVA infrastructure transformation project (fishing port section)
Project overview
Quanzhou Quangang New City Investment Co., Ltd. applied for 800kVA infrastructure transformation project (fishing port section)
Fund situation
Account arrival status
0
contract
Total contract price: 216,873. The contract stipulates 85% after passing the inspection.
Planned power delivery time
none
progress status
First completion acceptance on May 28, 2021. The second completion acceptance will be on October 16, 2023.
There is a problem
The user's project payment has not been paid.
Completion information
Lin Guirong
1. Quanzhou Entry-Exit Border Inspection Station of the People's Republic of China - Fujian Border Guard Corps Quanzhou (Southern Fujian) Border Inspection Troop Barracks Power Distribution Project
progress status
98%
There is a problem
The remaining cable ducts connecting the sidewalks will need to be constructed until workers enter the site on February 27 (planned to be completed in four days)
2Power distribution project of the inpatient building of the Donghai Branch of the Second Affiliated Hospital of Fujian Medical University
Progress:
98%
There is a problem:
The remaining floor paint needs to be applied after the electrical installation is completed
Electric power connection project outside the Jiangnan New District project - Electric power drainage pipe construction outside the Jiangnan New District Science and Technology Innovation Center project
progress status
98%
There is a problem
The industrial manhole covers (ductile iron manhole covers) are being rectified and are promised to be completed on March 15
Fund situation: 6979192 yuan
Labor subcontracting 1,387,920 yuan
Progress payment of RMB 1,320,239 has been paid
Material subcontracting 3,330,884 yuan
Progress payment of RMB 3,221,669 has been paid
Professional subcontracting 2,260,388 yuan
Progress payment of RMB 1,307,206 has been paid
Wen Shaowei
Project status in progress
Mingji Xintiandi Phase II
Project overview: 1 new switch room and power distribution room (2*1250KVA) and 1 commercial power distribution room (2*1250KVA) will be built.
Funding situation:
Payment status: 50%
The contract stipulates: The amount is 5.827671 million yuan, 50% after the contract, 40% after the equipment comes into the site, and 10% before power delivery.
Planned power delivery time: 2023.09.21
Progress: One household per meter has been supplied with electricity and the property transfer procedures have been completed, but the commercial part has not been supplied with electricity.
Problem: Due to the bankruptcy of the real estate company, the court has ruled that our company has priority in repaying the remaining 50% of the project payment, and the operation department will follow up later.
Completion information
Fengquan Business - Nanpushan Shantytown Resettlement Housing Project Power Distribution Project
Our version of the completed data is not approved by the owner, and part of the cost of design changes has not been confirmed by the owner. After coordination with many parties, the completion data and change procedures are being reorganized according to their requirements. The as-built drawings have been reprinted and stamped with a completion stamp. The designer replied that he will be available to stamp the drawings and design stamp next week, and will go to Fuzhou to handle the stamping matter when the time is confirmed.