MindMap Gallery Electrical installation engineering construction technology
Electrical installation engineering construction technology, including buried pipes and embedded parts, equipment installation, power-on trial operation, delivery for use, wire and cable laying, circuit connection, inspection and debugging.
Edited at 2021-11-28 15:42:16This Valentine's Day brand marketing handbook provides businesses with five practical models, covering everything from creating offline experiences to driving online engagement. Whether you're a shopping mall, restaurant, or online brand, you'll find a suitable strategy: each model includes clear objectives and industry-specific guidelines, helping brands transform traffic into real sales and lasting emotional connections during this romantic season.
This Valentine's Day map illustrates love through 30 romantic possibilities, from the vintage charm of "handwritten love letters" to the urban landscape of "rooftop sunsets," from the tactile experience of a "pottery workshop" to the leisurely moments of "wine tasting at a vineyard"—offering a unique sense of occasion for every couple. Whether it's cozy, experiential, or luxurious, love always finds the most fitting expression. May you all find the perfect atmosphere for your love story.
The ice hockey schedule for the Milano Cortina 2026 Winter Olympics, featuring preliminary rounds, quarterfinals, and medal matches for both men's and women's tournaments from February 5–22. All game times are listed in Eastern Standard Time (EST).
This Valentine's Day brand marketing handbook provides businesses with five practical models, covering everything from creating offline experiences to driving online engagement. Whether you're a shopping mall, restaurant, or online brand, you'll find a suitable strategy: each model includes clear objectives and industry-specific guidelines, helping brands transform traffic into real sales and lasting emotional connections during this romantic season.
This Valentine's Day map illustrates love through 30 romantic possibilities, from the vintage charm of "handwritten love letters" to the urban landscape of "rooftop sunsets," from the tactile experience of a "pottery workshop" to the leisurely moments of "wine tasting at a vineyard"—offering a unique sense of occasion for every couple. Whether it's cozy, experiential, or luxurious, love always finds the most fitting expression. May you all find the perfect atmosphere for your love story.
The ice hockey schedule for the Milano Cortina 2026 Winter Olympics, featuring preliminary rounds, quarterfinals, and medal matches for both men's and women's tournaments from February 5–22. All game times are listed in Eastern Standard Time (EST).
Electrical installation engineering construction technology
Buried pipes and embedded parts
device installation
Installation procedures for oil-immersed transformers
open box to check
Secondary transportation
Equipment in place
Lifting core inspection
Accessory installation
Oil filtering and oil filling
acceptance
Rhythm: The second uncle is newly rich, and they (break) up with each other again
Vacuum circuit breaker installation procedure
Vacuum circuit breaker inspection
Operating mechanism inspection
Vacuum circuit breaker in place
Mechanical and electrical performance testing
Installation procedures for sulfur hexafluoride circuit breakers
open box to check
Body installation
Filled with sulfur hexafluoride
Operating mechanism installation
Check and adjust
Insulation test
test
Tips: Open the six-machine test
Installation procedures for complete power distribution equipment
open box to check
Secondary transportation
Installation and fixation
Busbar installation
Secondary loop connection
Experimental adjustment
Power transmission operation acceptance
Tip: If you want to move an ancient tomb, try your hand a second time
Installation requirements for individual equipment
The storage and storage period of electrical equipment and equipment before installation should be in accordance with the manufacturer’s requirements.
Fireproof
Moisture proof
dust-proof
"Three precautions" for storage environment
Fasteners should be galvanized
After the transformer is installed in place, each ground lead section should be well grounded.
The secondary coil of the current transformer that is not used temporarily should be short-circuited and grounded.
When installing the zero sequence transformer, pay special attention to the distance from the surrounding magnetic conductors or live conductors.
There should be no jamming in the linkage between the circuit breaker and its operating mechanism, the opening and closing instructions should be correct, and the switch action should be correct and reliable.
The reactor should be installed so that the winding direction of the coil meets the load design requirements.
The discharge circuit of the capacitor should be complete and the grounding switch should be flexible in operation.
Installation requirements for complete sets of power distribution equipment
The ground contact of the handcart unit is reliably grounded
When advancing
Contact before the main contact
When pulling out
Open after the main contact
Wire and cable laying
Requirements for cable tray laying
The straight section of the metal bridge exceeds 30M
The straight section of the aluminum bridge exceeds 15M
There should be expansion joints or expansion sheets
Cable laying precautions
The cables should be laid from the centralized point of cable layout to the dispersed point of cable layout. Cables to the same end point should be laid at one time.
Lay long lines and large cross-sections first
The rear laying lines are short and the cross-section is small.
The cable should be capped within 4 hours after cutting.
Oil-impregnated paper insulated power cables must be lead sealed
Plastic insulated power cables should have moisture-proof ends
The oil-filled cable cutout must be higher than the adjacent two sides of the cable
Busbar installation
three phase colors
A yellow
B green
C red
Wang Leehom
Arrangement up and down
up and down
Horizontal arrangement
After-hours Before-hours
Down conductor layout
about
Loop closed
Inspection, testing, debugging
examine
Check that all relevant primary and secondary equipment installation and wiring should be completed, and all signs should be obvious, correct and complete. It is necessary to carry out the secondary circuit power check first, and then carry out the primary circuit power check.
The primary circuit has undergone insulation resistance measurement and withstand voltage testing, and the insulation resistance value complies with regulations. The insulation resistance measurement and withstand voltage test of the weak current circuit in the secondary circuit shall be carried out according to the manufacturer's regulations.
Already have AC and DC power supplies for reliable operation (circuit breaker), signaling and closing of secondary systems
The current and voltage transformers have passed electrical tests. There is no open circuit on the secondary side of the current transformer, and there is no short circuit on the secondary side of the voltage transformer.
Check that the relays and instruments in the circuit have been calibrated and passed the test
The circuit breaker and isolation switch of the inspection circuit have been adjusted, and the circuit breaker has undergone manual and electric tripping tests.
Handover test
Contents of handover test
Voltage(U)
Line phase check
Resistance(R)
Measure insulation resistance
Measure the DC resistance of conductors
Current(I)
DC withstand voltage test
AC withstand voltage test
Leakage current measurement
insulation
Insulating oil test
Electrical strength
Media loss angle tangent
spectrum analysis
Precautions for handover test
1. Barriers should be installed and warning signs should be hung around high-voltage test equipment and high-voltage lead wires.
2. When conducting high-voltage tests, there should be sufficient safety distance between the operator and the high-voltage circuit.
Voltage level 6-10KV without protection, minimum safety distance 0.7m
3. After the high-voltage test is completed, the DC test equipment and the equipment under test with large capacitance should be discharged multiple times.
Discharge time one minute
4. The AC withstand voltage test of the circuit breaker should be carried out in the opening and closing states respectively.
5. When conducting pressure withstand tests on complete sets of equipment, it is advisable to separate various equipment that are connected together and conduct them separately.
6. During the DC withstand voltage test, the test voltage is increased in stages according to 0.5 times the rated voltage for each level, and the leakage current is recorded.
Stay for 1 minute at each stage
Power on and test run
Power receiving steps
The secondary circuit test of the power receiving system has passed the test, and its protection setting value has been set according to actual requirements.
The equipment and cables of the power receiving system are well insulated.
Safety warning signs and fire protection facilities are in place
According to the approved power receiving operation instructions, organize the high-voltage side of the newly-built electrical system transformer to receive power from the grid side, and press the power distribution cabinet through the power distribution cabinet.
First high pressure then low pressure
Main line first, then branch line
Test power on step by step
After the trial power-on, the system works normally and the trial operation of the new project can be carried out.
Trial operation conditions and safety requirements of power supply system
Operating conditions
1. The electrical equipment is installed completely and the street circuit wiring is correct, complete and intact.
2. The phase sequence of the power supply circuit should be checked and the power supply and special power supply should meet the power supply conditions.
3. Electrical equipment should be checked after power-on, and the protection setting value of the power supply system has been set according to the design requirements.
4. The environment is clean and tidy, and the necessary sealing has been done
security requirements
The locking protection device of high-voltage switchgear must be intact and reliable
Prevent mis-closing and mis-opening of circuit breakers
Prevent opening and closing of isolating switch under load
Prevent live wires from hanging on the ground
Prevent live grounding switch from being closed
Prevent accidental entry of live electricity
Five-proof interlocking
Before the trial operation, check again whether the primary and secondary circuits are correct, and the live parts must be registered with safety signs.
During the trial operation of the power supply system
Implement a work ticket system for power transmission and power outage procedures
Implement a voting system for electrical operations
Electrical operators must undergo professional training and possess electrician special operation qualification certificates
Delivery