MindMap Gallery 7PMP-Project Cost Management Summary
Provides guidance on how to manage project costs, including policies, procedures and planning, documentation for managing, spending and controlling project costs, units of measurement, accuracy of cost estimates, links to organizational procedures, control thresholds, performance measurement rules, process descriptions, reports Format.
Edited at 2021-05-31 19:07:20This is a mind map about bacteria, and its main contents include: overview, morphology, types, structure, reproduction, distribution, application, and expansion. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about plant asexual reproduction, and its main contents include: concept, spore reproduction, vegetative reproduction, tissue culture, and buds. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about the reproductive development of animals, and its main contents include: insects, frogs, birds, sexual reproduction, and asexual reproduction. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about bacteria, and its main contents include: overview, morphology, types, structure, reproduction, distribution, application, and expansion. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about plant asexual reproduction, and its main contents include: concept, spore reproduction, vegetative reproduction, tissue culture, and buds. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about the reproductive development of animals, and its main contents include: insects, frogs, birds, sexual reproduction, and asexual reproduction. The summary is comprehensive and meticulous, suitable as review materials.
PMP-Project Cost Management
Standardized cost management
ITTO
enter
1. Project Charter
2. Project management plan
progress management plan
risk management plan
3. Business environment factors
4. Organizational process assets
Tools & Techniques
1. Expert judgment (experienced drivers guide me)
2.Analytical techniques
3.Meeting
output
1. Cost management plan
unit of measurement
Accuracy
Accuracy
Organization Program Links
control threshold
performance measurement rules
report format
Other details
Estimate cost
ITTO
enter
1. Project management plan
cost management plan
quality management plan
Scope Baseline
2.Project files
Lessons Learned Register
Project schedule
Resource requirements
risk register
3. Business environment factors
4. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Analogous estimation (similar projects in the past, low cost, less time-consuming, and low accuracy)
3. Parameter estimation (statistics of historical data, models and other variables)
4. Bottom-up estimation (specific and detailed estimation of individual work packages)
5. Three-point estimate (considering uncertainty and risk)
6.Data analysis
Analysis of alternatives (choose one A, B, or C)
Reserve analysis
Management reserves (unknown unknown risks)
Contingency reserves (known unknown risks)
quality cost
7. Project management information system
8. Decision-making (voting)
output
1. Cost estimation
Rough magnitude estimate (-25%~75%)
Budget estimate (-10%~ 25%)
Certainty estimate (-5%~10%)
2. Basis for estimation
3. Project file update
Hypothetical log
Lessons Learned Register
risk register
Control costs
ITTO
enter
1. Project management plan
cost management plan
cost basis
performance measurement benchmarks
2.Project files
Lessons Learned Register
3. Project funding requirements
4. Job performance data
5. Organizational process assets
Tools & Techniques
1. Expert judgment
2.Data analysis
Earned value analysis (actual schedule and cost performance compared with performance measures to derive status)
concept
EVM: Commonly used performance measurement method is earned value management
PV: planned value (what to do)
EV: Earned value (done)
AC: actual cost (spent)
index
Deviation analysis
Progress deviation: SV=EV-PV
Cost deviation: CV=EV-AC
Performance Analysis
Schedule Performance Index: SPI=EV/PV
Cost Performance Index: CPI=EV/AC
Deviation analysis (identify differences and decide whether corrective or preventive measures need to be taken by comparing planned costs with actual costs, focusing on the present)
Trend analysis (review changes in performance over time (improvement or deterioration), predict the future)
Reserve analysis (contingency reserves, management reserves)
3. Remaining performance index for completion (the cost performance index that the remaining work must achieve to achieve a specific goal)
concept
BAC: budget at completion
ETC: Cost budget required for completion
EAC: Estimate at Completion
index
Trend forecast
Atypical (no deviation will occur in the future)
ETC=BAC-EV
Typical (current deviation represents future trend)
ETC=(BAC-EV)/CPI
total cost of completion budget
new estimate
EAC=AC ETC
remaining estimate
EAC=AC (BAC-EV)
Use CPI
EAC=BAC/CPI
Calculated using SPI<1
EAC=BAC/(CPI*SPI)
Total Cost of Completion Variance
VAC=BAC-EAC
4. Project management information system
output
1. Job performance information
2. Cost forecast
3. Change request
4. Project management plan update
cost management plan
cost basis
performance measurement benchmarks
5. Project file update
Hypothetical log
Estimate basis
Cost Estimate
Lessons Learned Register
risk register
Budgeting
ITTO
enter
1. Project management plan
cost management plan
resource management plan
Scope Baseline
2.Project files
Estimate basis
Cost Estimate
Project schedule
risk register
3.Business documents
business documents
Benefit Management Plan
4. Agreement
5. Business environment factors
6. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Cost summary
Cost estimates are rolled up to the work packages in the WBS to the control account to arrive at the total cost
3.Data analysis
contingency reserve
management reserve
4. Review of historical information (historical relationship between parameter estimation or analogy estimation)
5. Funding limit balancing (any funding restrictions on the project, balancing fund expenditures)
6. Financing
output
1. Cost basis
2. Project funding requirements
3. Project file update
Cost Estimate
Project schedule
risk register
step
1. Calculate the costs required for each schedule activity
2. Summarize the work package costs
3. Summarize the costs of each work package to obtain the cost of the control account
4. Sum up the costs of each control account to obtain the cost of the project
other