MindMap Gallery 6PMP-Project Progress Management Summary
This is a mind map about 6PMP-Project Progress Management Summary. Project progress management refers to the use of scientific methods to determine progress goals, prepare progress plans and resource supply plans, conduct progress control, and achieve construction period goals on the basis of coordination with quality and cost goals. This mind map is compiled based on PMP reading notes. I hope it will be helpful to you!
Edited at 2021-05-31 17:18:43This is a mind map about bacteria, and its main contents include: overview, morphology, types, structure, reproduction, distribution, application, and expansion. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about plant asexual reproduction, and its main contents include: concept, spore reproduction, vegetative reproduction, tissue culture, and buds. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about the reproductive development of animals, and its main contents include: insects, frogs, birds, sexual reproduction, and asexual reproduction. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about bacteria, and its main contents include: overview, morphology, types, structure, reproduction, distribution, application, and expansion. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about plant asexual reproduction, and its main contents include: concept, spore reproduction, vegetative reproduction, tissue culture, and buds. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about the reproductive development of animals, and its main contents include: insects, frogs, birds, sexual reproduction, and asexual reproduction. The summary is comprehensive and meticulous, suitable as review materials.
PMP-Project Progress Management
Planning progress management
ITTO
enter
1. Project Charter
2. Project management plan
scope management plan
development method
3. Business environment factors
4. Organizational process assets
Tools & Techniques
1. Expert judgment
2.Data analysis
3.Meeting
output
1. Progress management plan
Project schedule model development
Accuracy
unit of measurement
Organization Program Links
Project schedule model maintenance
control threshold
performance measurement rules
Define activities
ITTO
enter
1. Project management plan
progress management plan
Scope Baseline
scope statement
WBS
WBS Dictionary
2. Business environment factors
3. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Decompose
3. Rolling planning
4.Meeting
output
1. Activity List (a comprehensive list of all schedule activities required for the project)
2. Activity attributes (similar to WBS dictionary)
3. Milestone list (important moments or events)
4. Change request
5. Project management plan update
progress baseline
cost basis
Sequence activities
ITTO
enter
1. Project management plan
progress management plan
Scope Baseline
2.Project files
Activity properties
Activity list
Hypothetical log
Milestone List
3. Business environment factors
4. Organizational process assets
Tools & Techniques
1. Predecessor Drawing Method (PDM)
Finish to start (FS)
Complete to Complete (FF)
Start to finish (SF)
Start to Start (SS)
Complete example
Duration = earliest finish (EF) - earliest start (ES)
Total time difference = latest finish (LF) - earliest finish (EF)
When the total time difference is 0 or a negative number, it is the critical path
2. Determine and integrate dependencies
mandatory dependencies
selective dependency
external dependencies
internal dependencies
3. Advance and lag
Lead time: the amount of time that the successor activity can be brought forward
Lag: The amount of time that the successor activity needs to be postponed
4. Project Management Information System (PMIS)
output
1. Project progress network diagram (PROJECT)
2. Project file update
Activity properties
Activity list
Hypothetical log
Milestone List
Estimate activity duration
ITTO
enter
1. Project management plan
progress management plan
Scope Baseline
2.Project files
Activity properties
Activity list
Hypothetical log
Lessons Learned Register
Milestone List
Project team dispatches work orders
resource breakdown structure
Resource Calendar
Resource requirements
risk register
3. Business environment factors
4. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Analogous estimation (similar projects in the past were low-cost, less time-consuming, and less accurate)
3. Parameter estimation (using statistical relationships between historical data and other variables, database)
4. Three-point estimation (consider uncertainties and risks in estimation)
Triangular distribution tE=(t0 tM tP)/3
Beta distribution tE=(t0 4tM tP)/6
5. Top-down vs. bottom-up
Top-down (analog estimation)
Bottom-up estimation
6.Data analysis
Alternatives Analysis
Reserve analysis
7.Decision making
8.Meeting
output
1. Duration estimation
2. Basis for estimation
3. Project file update
Activity properties
Hypothetical log
Lessons Learned Register
Develop a progress plan
ITTO
enter
1. Project management plan
progress management plan
Scope Baseline
2. project files
Activity properties
Activity list
Hypothetical log
Estimate basis
duration estimate
Lessons Learned Register
Milestone List
Project progress network diagram
Project team dispatches work orders
Resource Calendar
Resource requirements
risk register
3. Agreement
4. Business environment factors
5. Organizational process assets
Tools & Techniques
1. Progress network analysis (calculate earliest and latest start date, earliest and latest completion date)
Critical path (regardless of resource constraints)
Critical chain method (considering resource constraints)
Resource optimization technology
Modeling techniques (what-if scenario analysis and resource leveling)
Schedule type
Project progress network diagram (including logical relationships)
Gantt Chart (Summary Schedule)
Milestone Chart (Milestone Progress Plan)
2. Critical path method (regardless of resource constraints, forward and backward analysis along the progress network path)
Total float (one task)
Free float time (between A-B)
Lead amount (the amount of time that the successor relationship is ahead of time)
Hysteresis (the amount of time that a successor relationship needs to be delayed)
3. Resource optimization
resource balancing
Parallel to series
Leading to changes in the critical path may lead to extension of the construction period
Target key resources
After the critical path is determined and before resource smoothing
Resource smoothing
Non-critical activities move back and forth
No changes to the critical path and no delay in completion dates
It may not be possible to optimize all resources
4.Data analysis
Modeling techniques, what-if scenario analysis
What if scenario X occurs?
subtopic
subtopic
simulation
Monte Carlo analysis: What-if scenario analysis, if A occurs, what about B?
Model individual risks and other sources of uncertainty
5. Advance and lag
6. Progress compression
rush work
Add money and resources
Increased costs
Increasing resources can shorten the duration
Quick follow up
Execute activities in parallel that would normally be performed sequentially
Increased rework and increased risk
Reduce duration through parallel activities
Convert series to parallel
7. Project Management Information System (PMIS)
8. Agile release planning
output
1. Progress benchmark
2. Project schedule
3. Progress data
4. Project Calendar
5.Change request
6. Project management plan update
progress management plan
cost basis
7. Project file update
Activity properties
Hypothetical log
duration estimate
Lessons Learned Register
Resource requirements
risk register
control progress
ITTO
enter
1. Project management plan
progress management plan
progress baseline
Scope Baseline
performance benchmark
2.Project files
Lessons Learned Register
Project Calendar
Project schedule
Resource Calendar Progress Data
3. Job performance data
4. Organizational process assets
Tools & Techniques
1.Data analysis
Earned value analysis
Schedule Variance (SV)
Schedule Performance Data (SPI)
Iterative burndown chart
Track the work that remains to be done in the iteration backlog)
performance review
Compare and analyze schedule performance
trend analysis
Examine project performance over time to see whether it is improving or deteriorating
Deviation analysis
Actual start and finish deviations from planned
What-if scenario analysis
Evaluate various scenarios
2. Critical path method
3. Project management information system
4. Resource optimization
5. Advance and lag
6. Progress compression
output
1. Job performance information
2. Progress forecast
3. Change request
4. Project management plan update
progress management plan
progress baseline
cost basis
performance measurement benchmarks
5. Project file update
Hypothetical log
Estimate basis
Lessons Learned Register
Project schedule
Resource Calendar
risk register
progress data