MindMap Gallery Real estate project completion acceptance mind map
Real estate completion acceptance, administrative acceptance, completion joint acceptance, project completion acceptance, real estate acceptance, real estate completion acceptance, project completion acceptance.
Edited at 2024-01-28 19:35:02This is a mind map about bacteria, and its main contents include: overview, morphology, types, structure, reproduction, distribution, application, and expansion. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about plant asexual reproduction, and its main contents include: concept, spore reproduction, vegetative reproduction, tissue culture, and buds. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about the reproductive development of animals, and its main contents include: insects, frogs, birds, sexual reproduction, and asexual reproduction. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about bacteria, and its main contents include: overview, morphology, types, structure, reproduction, distribution, application, and expansion. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about plant asexual reproduction, and its main contents include: concept, spore reproduction, vegetative reproduction, tissue culture, and buds. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about the reproductive development of animals, and its main contents include: insects, frogs, birds, sexual reproduction, and asexual reproduction. The summary is comprehensive and meticulous, suitable as review materials.
Real estate project completion acceptance mind map
Category one (Obtaining sufficient and necessary conditions for project completion filing)
1. "Planning Verification Opinion Letter"
Planning acceptance
1. Landscaping completed
2. Basement marking completed
3. Complete measurement reports for each building
4. Each major will stamp the completed drawings
2. "Fire Protection Acceptance Letter"
Fire inspection
1. Fire protection project completed
2. Issuance of fire engineering inspection report
3. Completion of on-site as-built drawings
3. "Civil Air Defense Acceptance Letter"
Civil air defense acceptance
1. The civil air defense project is completed;
2. Complete the civil air defense inspection data;
4. "Quality Supervision Report"
Quality supervision and acceptance
Construction work completed
Installation work completed
Household fine decoration passed the acceptance inspection
Garden project completed
Internal preliminary inspection and rectification completed
5. "Archives Acceptance Opinions"
File pre-acceptance
1. Preliminary procedures related to the construction unit
2. Materials related to the construction unit
3. Relevant acceptance approval (category one, category two)
Category 2 (Non-critical administrative acceptance)
1. Lightning protection acceptance
1. The lightning protection project is completed;
2. The lightning protection data has been sorted out.
2. Energy saving acceptance
1. The energy-saving project is completed;
2. Completion of energy-saving project data;
3. Acceptance of reclaimed water and water saving
1. The installation of reclaimed water facilities is completed;
2. Issue a water quality test report;
3. Complete the water saving acceptance report;
4. Environmental protection acceptance
1. The environmental protection project is completed;
2. The dangerous goods storage room is completed (none);
3. The generator room is completed.
5. National Security Acceptance
1. The intelligent system and security system are completed;
2. Issue a weak current project inspection report;
6. Garden acceptance
1. The garden project is completed;
2. Issue completed garden drawings and general plant configuration drawings;
7. Soil and water conservation acceptance
1. Prepare soil and water conservation acceptance plan;
2. The earthworks are completed;
3. Garden planting soil is completed;
Category three (Non-necessary conditions for administrative acceptance and delivery)
1. Elevator engineering
Factory inspection and acceptance
Pot inspection and acceptance
Acceptance certificate
2. Power distribution engineering
High voltage acceptance qualified
Meter reading project delivered to household passed acceptance test
Sign the agreement
transfer
(Charging pile supporting project)
3. Water supply project
water quality report
(Water supply project acceptance letter)
(meter reading at home)
4. Gas engineering
Engineering construction
Municipal connection
Pressure regulating box
Pipe network construction
ground
main body
Ventilation acceptance opinion letter
5. Communication engineering
Municipal connection
Park pipe network to weak electrical room
Letter of Acceptance from the Traffic Management Bureau
Three major operators connect
Property application network opened
Intelligent engineering debugging