MindMap Gallery [Second Level Construction Engineer's Notes--Construction Management] Dynamic Control of Construction Engineering Project Goals
[Second Level Construction Engineer's Notes--Construction Project Construction Management--Dynamic Control of Construction Project Project Objectives under the Construction Management Chapter.
Edited at 2021-05-22 00:35:25This is a mind map about bacteria, and its main contents include: overview, morphology, types, structure, reproduction, distribution, application, and expansion. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about plant asexual reproduction, and its main contents include: concept, spore reproduction, vegetative reproduction, tissue culture, and buds. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about the reproductive development of animals, and its main contents include: insects, frogs, birds, sexual reproduction, and asexual reproduction. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about bacteria, and its main contents include: overview, morphology, types, structure, reproduction, distribution, application, and expansion. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about plant asexual reproduction, and its main contents include: concept, spore reproduction, vegetative reproduction, tissue culture, and buds. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about the reproductive development of animals, and its main contents include: insects, frogs, birds, sexual reproduction, and asexual reproduction. The summary is comprehensive and meticulous, suitable as review materials.
Dynamic control of construction project goals
Dynamic control principle
Dynamic control steps
Preparation
Decompose goals such as investment/cost, schedule and quality goals to derive planned values
Dynamically track and control project goals during project implementation
Collect actual values for project goals
Regular comparison of planned and actual values
Compare, if there is any deviation, take corrective measures to correct the deviation
Make target adjustments if necessary
Corrective measures for dynamic control of project goals
organizational measures
Analyze problems that affect the realization of project goals due to organizational reasons, and take corresponding measures, such as adjusting the project organizational structure, task division, management function division, work flow and project management team personnel, etc.
Organizational theory and personnel deployment
Management measures (including contractual measures)
Analyze problems that affect the realization of project goals due to management reasons, and take corresponding measures, such as adjusting progress management methods and means, changing construction management and strengthening contract management
Management ideas, methods and means, changing construction management and strengthening contract management
economic measures
Analyze the problems that affect the realization of project goals due to economic reasons, and take corresponding measures, such as implementing the funds needed to speed up the progress of project construction, etc.
Funds, resources, economic incentives
technical measures
Analyze problems that affect the realization of project goals due to technical reasons (including design and construction technology), and take corresponding measures, such as adjusting the design, improving construction methods, and changing construction tools, etc.
Adjust design, change machines, change materials, select methods, and choose solutions
Prior control of project goals
The core of dynamic control of project goals is to regularly compare the planned values and actual values of the project goals during the project implementation process, and take corrective measures when it is found that the project goals deviate
In order to avoid the occurrence of project target deviation, we should also pay attention to proactive control beforehand, that is, analyze in advance various influencing factors that may cause the project target deviation and take effective preventive measures.
Application of dynamic control methods in construction management
Control construction progress
1. Layer-by-layer decomposition of goals
(Large-scale projects decompose progress targets layer by layer by preparing the overall construction progress plan, overall progress plan, project subsystems and construction progress plans of each sub-project)
2. Dynamic tracking and control
Collect actual construction progress values
Regularly conduct quantitative comparisons between planned and actual construction progress values
control cycle
Generally one month, for important projects it can be positioned for ten days or one week
The results of the comparison between schedule plan values and actual values are reflected in progress tracking and control reports (such as the preparation of ten-day, monthly, quarterly, half-year and annual reports for precision control, etc.)
3. If deviations in progress are found, make corrections
4. Adjust target value if necessary
Control construction costs
1. Goal decomposition
By preparing construction cost planning, analyze and demonstrate the possibility of achieving construction cost targets, and decompose construction cost targets.
2. Dynamic tracking and control
collect actual values
Quantitative comparison of actual values and planned values in construction cost control (period: one month)
3. If deviations in progress are found, make corrections
4. Adjust cost targets if necessary
5 comparisons
Bid price - contract price
Contract price--construction cost planning
Contract price--actual construction cost
Contract price--project payment
Construction cost planning--actual construction cost
Control construction quality
1. Goal decomposition
Quality plan value of each element of project quality
2. Dynamic tracking and control
collect actual values
Regularly track and control planned and actual values
3. If deviations in progress are found, make corrections
It includes not only the construction quality of each sub-project, but also materials, semi-finished products, finished products and related equipment.