MindMap Gallery PMP ITTO Unit9 Resource
The ITTO mind map for PMP exam preparation is purely handmade and can be edited after downloading. I hope it will help you pass the PMP exam and get the PMP certificate. You can follow me if you like.
Edited at 2021-03-30 15:13:33This is a mind map about bacteria, and its main contents include: overview, morphology, types, structure, reproduction, distribution, application, and expansion. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about plant asexual reproduction, and its main contents include: concept, spore reproduction, vegetative reproduction, tissue culture, and buds. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about the reproductive development of animals, and its main contents include: insects, frogs, birds, sexual reproduction, and asexual reproduction. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about bacteria, and its main contents include: overview, morphology, types, structure, reproduction, distribution, application, and expansion. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about plant asexual reproduction, and its main contents include: concept, spore reproduction, vegetative reproduction, tissue culture, and buds. The summary is comprehensive and meticulous, suitable as review materials.
This is a mind map about the reproductive development of animals, and its main contents include: insects, frogs, birds, sexual reproduction, and asexual reproduction. The summary is comprehensive and meticulous, suitable as review materials.
9.1 Plan Resource Management
ITTO
Inputs
1. Project charter
2. Project management plan
(1) Scope baseline
(2) Quality management plan
3. Project documents
(1) Project schedule
(2) Requirements documentation
(3) Risk register
(4) Stakeholder register
4. Enterprise environmental factors
5. Organizational process assets
9.2 Estimate Activity Resources
ITTO
Inputs
1. Project management plan
(1) Resource management plan
(2) Scope baseline
2. Project documents
(1) Activity attributes
(2) Activity list
(3) Assumption log
(4) Cost estimates
(5) Resource calendars
(6) Risk register
3. Enterprise environmental factors
4. Organizational process assets
9.3 Acquire Resources
ITTO
Inputs
1. Project management plan
(1) Resource management plan
(2) Procurement management plan
(3) Cost baseline
2. Project documents
(1) Project schedule
(2) Resource calendars
(3) Resource requirements
(4) Stakeholder register
3. Enterprise environmental factors
4. Organizational process assets
9.4 Develop Team
ITTO
Inputs
1. Project management plan
(1) Resource management plan
2. Project documents
(1) Project schedule
(2) Resource calendars
(3) Lessons learned register
(4) Project team assignments
(5) Team charter
3. Enterprise environmental factors
4. Organizational process assets
9.5 Manage Team
ITTO
Inputs
1. Project management plan
(1) Resource management plan
2. Project documents
(1) Issue log
(2) Lessons learned register
(3) Project team assignments
(4) Team charter
3. Work performance reports
4. Team performance assessments
5. Enterprise environmental factors
6. Organizational process assets
9.6 Control Resources
ITTO
Inputs
1. Project management plan
(1) Resource management plan
2. Project documents
(1) Issue log
(2) Lessons learned register
(3) Project team assignments
(4) Project schedule
(5) Resource breakdown structure
(6) Resource requirements
(7) Risk register
3. Work performance data
4. Agreements
5. Organizational process assets
The end
ITTO
Tools and Techniques
1. Data analysis
(1) Alternatives analysis
(2) Cost-benefit analysis
(3) Performance reviews
(4) Trend analysis
2. Problem solving
3. Interpersonal and team skills
(1) Negotiation
(2) Influencing
4. Project management information system
Outputs
1. Work performance information
2. Change requests
3. Project management plan updates
(1) Resource management plan
(2) Schedule baseline
(3) Cost baseline
4. Project documents updates
(1) Lessons learned register
(2) Resource breakdown structure
(3) Risk register
(4) Assumption log
(5) Issue log
Outputs
1. Change requests
2. Project management plan updates
Resource management plan
Schedule baseline
Cost baseline
3. Project documents updates
(1) Issue log
(2) Lessons learned register
(3) Project team assignments
4. Enterprise environmental factors updates
Tools and Techniques
1. Virtual teams
2. communication technology
3. Interpersonal and team skills
(1) Conflict management
(2) Decision making
(3) Emotional intelligence
(4) Influencing
(5) Leadership
4. Project management information system
Tools and Techniques
1. Virtual teams
2. communication technology
3. Interpersonal and team skills
(1) Conflict management
(2) Influencing
(3) Motivation
(4) Negotiation
(5) Team building
4. Recognition and rewards
5. Training
6. Individual and team assessments
7. Meetings
Outputs
1. Team performance assessments
2. Change requests
3. Project management plan updates
(1) Resource management plan
4. Project documents updates
(1) Lessons learned register
(2) Project schedule
(3) Project team assignments
(4) Resource calendars
(5) Team charter
5. Enterprise environmental factors updates
6. Organizational process assets updates
Outputs
1. Physical resource assignments
2. Project team assignments
3. Resource calendars
4. Change requests
5. Project management plan updates
(1) Resource management plan
(2) Cost baseline
6. Project documents updates
(1) Lessons learned register
(2) Project schedule
(3) Resource breakdown structure
(4) Resource requirements
(5) Risk register
(6) Stakeholder register
7. Enterprise environmental factors updates
8. Organizational process assets updates
Tools and Techniques
1. Decision making
(1) Multicriteria decision analysis
2. Interpersonal and team skills
(1) Negotiation
3. Pre-assignment
4. Virtual teams
Tools and Techniques
1. Expert judgment
2. Bottom-up estimating
3. Analogous estimating
4. Parametric estimating
5. Data analysis
(1) Alternatives analysis
6. Project management information system
7. Meetings
Outputs
1. Resource requirements
2. Basis of estimates
3. Resource breakdown structure
4. Project documents updates
(1) Activity attributes
(2) Assumption lo
(3) Lessons learned register
Unit9 PROJECT RESOURCE MANAGEMENT ITTO
Outputs
1. Resource management plan
2. Team charter
3. Project documents updates
(1) Assumption log
(2) Risk register
Tools and Techniques
1. Expert judgment
2. Data representation
(1) Hierarchical charts
(2) Responsibility assignment matrix
(3) Text-oriented formats
3. organizational theory
4. Meetings