ERP Launching

Plan BERP Launching SchedulePrepare1/1 - 1/20 : 15.0 DayProgram & Design2/5 - 6/2 : 85.0 DayLaunching6/27 - 7/3 : 4.0 DayMaintenanceInformation collectionFunction discussionAdam; Daniel; Edward1/1 - 1/13 : 2.0 WeekSKU discussionBOM CollectionLuis1/15 - 1/20 : 5.0 DayProgrammingGeorge; Harry; Karen2/5 - 5/5 : 3.0 MonthUI DesignBeatrice; Cathy3/23 - 4/21 : 1.0 MonthTest5/14 - 5/26 : 2.0 WeekFix bugsGeorge5/14 - 6/2 : 15.0 Day Launching7/2 - 7/3 : 1.0 DayERP TrainingEdward; Jessie6/27 - 6/30 : 3.0 DayCollect feedbacksIcy7/2 - 7/14 : 2.0 WeekOptimize systemIT DepartmentEdwardOperation DepartmentAdamSupply Chain DepartmentDanielLaunch earlierdelaycancelERP Fumction ConfirmationFiona1/24 - 1/25 : 1.0 DaySuppliersCustomersSales